Applied Digital (APLD) signed an 18-year lease for 150 MW of capacity with a tier-one investment-grade hyperscaler, worth about $5.4 billion in base-term revenue. Shares were little changed at 3:59 p.m. ET.

Key takeaways

  • Applied Digital (APLD) entered into an 18-year lease with a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity, with about $5.4 billion in base-term contracted revenue. Delivery is anticipated to begin in the first half of calendar 2028. The company also raised its preferred equity purchase commitment to $2.50 billion and closed a $300 million bridge loan.
Applied Digital logo

Applied Digital (APLD) signed an 18-year lease with a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity at one of its data center campuses. The lease provides about $5.4 billion in base-term contracted revenue, or about $12.7 billion if all renewal options are exercised over a 33-year total term.

Shares were little changed at 3:59 p.m. ET, from a $12.22 close.

With this lease, total contracted base-term lease revenue exceeds $41 billion, or nearly $100 billion with all renewal options. The lease carries improved terms over prior leases, including higher pricing.

The portfolio now totals more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load. About 75% of total contracted base-term lease revenue is attributable to investment-grade customers.

Delivery is anticipated to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals.

Chief Financial Officer Saidal Mohmand said the build will be funded by equity already on the balance sheet and a $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing supported by the lease.

The company expects to complete the remaining project finance for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027, with Delta Forge 2 to follow in the second calendar quarter of 2027.

A letter agreement raises the aggregate commitment under its Preferred Equity Purchase Agreement, dated April 30, 2025, from $2.00 billion to $2.50 billion. The agreement covers the existing Series G Convertible Preferred Stock. About $1.04 billion remains available to be drawn.

An indirect subsidiary closed a $300 million senior secured bridge facility: a delayed draw term loan with a 364-day maturity, bearing interest at the Secured Overnight Financing Rate plus 300 basis points. The loan is secured by the project's assets and can be prepaid at any time without premium.

Draws are subject to construction milestones, regulatory approvals, including state commission approval of electrical rates, lender consents and certain financial covenants.

The facility funds continued development and construction of Delta Forge 1 in Louisiana, which is backed by a long-term lease with a U.S. based, tier-one investment-grade hyperscaler. The company expects to seek additional financing to complete construction at that campus.